Mobile cranes lift a conveyor gallery section at Esperance Port, with the ship loader and stacked containers behind

Esperance Port Shiploader and Conveyor Demolition

More than 520 tonnes of redundant steel structure removed at Berth 2, clearing a safe and accessible wharf for Southern Ports.

Location
Esperance, WA
Client
Southern Ports
Duration
July to October 2021
Contract type
Lump sum
Steel removed
520 tonnes

Esperance Port is a pivotal trading hub connecting regional Western Australian industries to global markets. With shipping methods modernising and upgrades planned, the long redundant 4,000 tonne-per-hour minerals shiploader and conveyor system at Berth 2 had to be removed. CareyMC was engaged by Southern Ports to undertake this Class 1 demolition project.

Aerial view of the berth, with the shiploader on the wharf and stacked containers

Over520 t

Fabricated steel removed

Over28 m

Height of the tallest structures

4,000 t/h

Capacity of the redundant shiploader

Scope of work

  • Removal of the existing berth face shiploader
  • Removal of the feed conveyor galleries and transfer towers
  • Strengthening of gallery trestles to support the sulphur import system, which was retained

The project demolished more than 520 tonnes of fabricated steel structures, some of them over 28 m high.

Key achievements

Keeping the sulphur import system in service let CareyMC show its capability in shutdown work on conveyor systems. The conveyor was shortened and a new tail-end gallery installed, all within tight permitted outages.

The team worked closely with Port Operations so that neither shipping nor the project was held up. Disruptive works were planned around the shipping schedule, and detailed traffic management plans kept landside transport moving at the port.

An elevating work platform beneath the conveyor gallery A crane lifts a section of the shiploader against a clear sky A conveyor gallery section held by a crane above the wharf Mobile cranes working beside the conveyor structure

More projects

All civil projects
  • Open trench with a new pipeline beside conveyors and stacked containers at Esperance Port

    Southern Ports Authority · Esperance WA · Aug - Oct 2020

    Esperance Port Diesel Pipeline

    A new DN350 diesel pipeline and connection pit at Esperance Port, replacing buried and under-wharf pipework with no interruption to through traffic.

  • Road bridge over a rock-armoured channel of clear green water at Bandy Creek

    Italia Stone Group / Department of Transport · Esperance WA · Aug 2019 - Apr 2020

    Bandy Creek Weir Reinstatement

    Bridge construction and the structural and services works for the new Bandy Creek weir at Esperance, delivered under subcontract.

  • Steel truss gangway reaching out over the water to a ferry pontoon on the Tiwi Islands

    Tiwi Enterprise Pty Ltd · Tiwi Islands NT · Sept 2018 - Nov 2019

    Tiwi Islands Ferry Terminals and Visitor Centre

    A visitor centre and two ferry landings, one on each side of the Apsley Strait, delivered by two Indigenous-owned businesses.

Ground to move? Let's talk.

Talk with our Civil Team