Fremantle Port Fender Replacement

Demolition and Replacement of Ship Fender Systems at a working port

Location: Fremantle Port
Client: Fremantle Port Authority
Duration July to October 2023
Contract Type: Lump Sum

The fender system at H Berth had reached the end of its life, becoming outdated and damaged. Carey was awarded the tender to remove the redundant system and replace it with a new, modern fender system.

Scope of Work:

  • Removal:
    • Removal of the existing steel pylon fender system
  • Installation:
    • Tie-in of the new fender support to the existing concrete deck
  • Operational Considerations:
    • Working around a live port, ensuring the protection of ships and mooring lines during demolition
    • Adhering to tight timelines during port shutdowns and between shipping schedules

Innovative Techniques:

Carey employed several innovative techniques on this project to improve efficiency and reduce risk:

  • Hydro-Demolition Robot:
    Used to remove selected areas of concrete without damaging the reinforcing structures
  • Mobile Booth:
    Erection of a mobile booth to contain demolition activities and protect ships in berth
  • Mobile Counter-Weight Scaffolds:
    Temporary supports that can be easily moved when ships need to berth

Several of these initiatives have now become standard practice at Fremantle Port.

Key Achievement:

This project is a strong example of Carey’s ability to deliver technically complex work in challenging environments, adhering to demanding schedules and site constraints.