Demolition and remediation of the Pier Hotel site on The Esplanade, Port Hedland, from hazardous materials removal to a cleared, restored site.
- Location
- The Esplanade, Port Hedland WA
- Timing
- May to Jul 2025
- Scope
- Demolition and remediation
Carey safely removed and disposed of asbestos, lead-based paints, synthetic mineral fibres and PCB fixtures, then demolished 10 structures, including their concrete footings, internal roads and parking, and eliminated the buried services.
All demolition debris was removed and the site restored, leaving level, cleared ground on The Esplanade.

10
Structures demolished
Including concrete footings, internal roads and parking
4
Hazardous materials removed
Asbestos, lead-based paints, synthetic mineral fibres and PCB fixtures
Restored
Final site
All demolition debris removed
Scope of work
- Safe removal and disposal of asbestos, lead-based paints, synthetic mineral fibres and PCB fixtures
- Demolition of 10 structures
- Removal of concrete footings, internal roads and parking
- Elimination of buried services
- Complete removal of demolition debris and site restoration
The result
A cleared, level site on The Esplanade, with every structure, footing and buried service removed.
Gallery
More projects
-

Boodarie Demolition
Demolished large steel-framed warehouses and single-storey buildings, leaving a cleared site.
-

Esplanade Hotel, Port Hedland
Redevelopment of the heritage two and three-storey stone hotel, from demolition and bulk excavation through concrete, structural steel and cladding to finished verandahs, courtyard, fencing and turf.
-

Beverley Town Water Tank Demolition
Demolished four redundant concrete water tanks, removed asbestos pipes and equipment, recycled the crushed concrete and steel, and finished two weeks ahead of schedule.