Outback Highway, Great Central Road

An alliance with Main Roads WA and Central Earthmoving to seal the first 40 km of the Great Central Road east of Laverton, part of the 2,700 km Outback Way.

Client
Main Roads WA
Location
Great Central Road, Laverton WA
Duration
December 2019 to September 2021
Contract
Wongutha Way Alliance

The Outback Way is a 2,700 km route from Laverton in Western Australia to Winton in Queensland via Alice Springs, often called Australia’s Longest Shortcut. More than 1,400 km of it remains unsealed, including almost 800 km of the Great Central Road, the Western Australian section.

In December 2019 the Wongutha Way Alliance was formed between Main Roads Western Australia, CareyMC and Central Earthmoving to deliver Work Package 1: 40 km of sealed road on the Great Central Road heading east from Laverton. The alliance set out to make best use of the budget, to maximise the length and extent of improvement, and to maximise local business and local Aboriginal participation and employment through the works.

Rollers working in line along the new road formation

40 km

Sealed road constructed

In a remote location, three weeks ahead of the revised schedule

0.00

LTIFR

Over40%

Aboriginal site hours

17% of all site hours by local Aboriginal people

24.8%

Spent with local business

Of contract value

Scope of works

  • Water drilling and water infrastructure construction
  • Gravel pit establishment and rehabilitation
  • Embankment foundation and earthworks
  • Pavement construction
  • Drainage installation
  • Sealing of the road
  • Signs and line marking
  • Design development for future work packages

Timeline

Work began on site in early 2020 with water drilling and gravel investigations, in an area known for limited supplies. The investigations succeeded: all basecourse gravel and construction water was sourced from along the road alignment.

Road construction began in earnest in August 2020. Practical completion of the 40 km was reached on 17 September 2021, three weeks ahead of the revised schedule.

Training

Two training programs were delivered over the project, upskilling previously untrained people in civil construction.

What Outback Way means to the community

Video: Main Roads Western Australia

Aerial view of the road alignment running straight through red country The crew stands in front of a Carey-branded truck Four crew members in high-visibility clothing beside a site vehicle Alliance partners gathered in a meeting room Two crew members beside a wheel loader A crew member stands beside a wheel loader

More projects

All civil projects
  • A freshly sealed highway with new line marking curves past road signs for Great Ocean Drive and Esperance

    Main Roads WA · Esperance WA

    South Coast Highway Upgrade

    Road widening and safety improvements at two Black Spot intersections on the main road into Esperance, for Main Roads WA.

  • Aerial view of a newly sealed heavy vehicle parking bay looping off a straight highway through red earth and scrub near Kambalda, in WA's Goldfields

    Main Roads WA · Kambalda WA · Dec 2021 - May 2022

    Kambalda Truck Parking and Hardstand

    A new heavy vehicle parking bay and rest stop outside Kambalda for Main Roads WA, with Aboriginal engagement targets exceeded four and five times over.

  • Aerial view of the renewed container hardstand at Esperance port, beside the ship loader

    Southern Ports Authority · Esperance WA · 2023 · $9.25M

    Berth 2 Hardstand Renewal

    A renewed container hardstand and a 220 kL stormwater holding tank at Esperance Port, delivered while the berth stayed open.