Outback Highway, Great Central Road
An alliance with Main Roads WA and Central Earthmoving to seal the first 40 km of the Great Central Road east of Laverton, part of the 2,700 km Outback Way.
- Client
- Main Roads WA
- Location
- Great Central Road, Laverton WA
- Duration
- December 2019 to September 2021
- Contract
- Wongutha Way Alliance
The Outback Way is a 2,700 km route from Laverton in Western Australia to Winton in Queensland via Alice Springs, often called Australia’s Longest Shortcut. More than 1,400 km of it remains unsealed, including almost 800 km of the Great Central Road, the Western Australian section.
In December 2019 the Wongutha Way Alliance was formed between Main Roads Western Australia, CareyMC and Central Earthmoving to deliver Work Package 1: 40 km of sealed road on the Great Central Road heading east from Laverton. The alliance set out to make best use of the budget, to maximise the length and extent of improvement, and to maximise local business and local Aboriginal participation and employment through the works.

40 km
Sealed road constructed
In a remote location, three weeks ahead of the revised schedule
0.00
LTIFR
Over40%
Aboriginal site hours
17% of all site hours by local Aboriginal people
24.8%
Spent with local business
Of contract value
Scope of works
- Water drilling and water infrastructure construction
- Gravel pit establishment and rehabilitation
- Embankment foundation and earthworks
- Pavement construction
- Drainage installation
- Sealing of the road
- Signs and line marking
- Design development for future work packages
Timeline
Work began on site in early 2020 with water drilling and gravel investigations, in an area known for limited supplies. The investigations succeeded: all basecourse gravel and construction water was sourced from along the road alignment.
Road construction began in earnest in August 2020. Practical completion of the 40 km was reached on 17 September 2021, three weeks ahead of the revised schedule.
Training
Two training programs were delivered over the project, upskilling previously untrained people in civil construction.
What Outback Way means to the community
Video: Main Roads Western Australia
Gallery
More projects
-

South Coast Highway Upgrade
Road widening and safety improvements at two Black Spot intersections on the main road into Esperance, for Main Roads WA.
-

Kambalda Truck Parking and Hardstand
A new heavy vehicle parking bay and rest stop outside Kambalda for Main Roads WA, with Aboriginal engagement targets exceeded four and five times over.
-

Berth 2 Hardstand Renewal
A renewed container hardstand and a 220 kL stormwater holding tank at Esperance Port, delivered while the berth stayed open.