Berth 2 Hardstand Renewal
A renewed container hardstand and a 220 kL stormwater holding tank at Esperance Port, delivered while the berth stayed open.
- Location
- Esperance, WA
- Client
- Southern Ports
- Duration
- January to September 2023
- Contract type
- Lump sum
Esperance Port, 720 km south-east of Perth, is the only deep-sea port in southern Western Australia and a gateway for many commodities. The Berth 2 Hardstand Renewal Project upgraded the berth’s infrastructure so that its environmental licence requirements are met.
Stormwater now passes through a new 220 kL holding tank, the First Flush Tank, and then a Dissolved Metals Treatment tank that removes metals and hydrocarbons before the water is released to the ocean. The project replaced the berth’s ineffective drainage system in full.
The hardstand itself was replaced as well. The existing pavement was excavated 520 mm and a new 340 mm basecourse placed and stabilised with 5% cement, a robust foundation for 180 mm of asphalt.

220 kL
First Flush Tank
Stormwater holding tank
2,500 kL/day
Dewatering
Pumped during tank construction
96 m
Sheet pile cofferdam
12 m deep, to support the tank works
180 mm
Asphalt
On a cement-stabilised basecourse
Scope of works
- Hardstand drainage: 225 m of 450 mm pipe, 50 m of 750 mm pipe and five reinforced concrete stormwater pits
- Pavement cement stabilisation and a 180 mm asphalt layer
- Temporary works: a 96 m sheet pile cofferdam, 12 m deep, to support construction of the tank
- Dewatering, pumping 2,500 kL a day
- Construction of the 220 kL First Flush Tank and installation of the Dissolved Metals Treatment tank
- Electrical and mechanical support
- Management of port user access throughout
Delivery
Berth 2 is busy, and it was critical that it remained operational at all times. The works were sequenced in multiple stages to achieve that, to the satisfaction of Port Operations and other stakeholders.
A highlight was the recycling of the demolished asphalt and concrete. It was crushed, screened and reused to create a new laydown area for Port Operations.
More projects
-

Fremantle Port Fender Replacement
Demolition and replacement of the ship fender system at H Berth, carried out at a working port.
-

Esperance Port Shiploader and Conveyor Demolition
More than 520 tonnes of redundant steel structure removed at Berth 2, clearing a safe and accessible wharf for Southern Ports.
-

Esperance Port Diesel Pipeline
A new DN350 diesel pipeline and connection pit at Esperance Port, replacing buried and under-wharf pipework with no interruption to through traffic.