Aerial view of a newly sealed heavy vehicle parking bay looping off a straight highway through red earth and scrub near Kambalda, in WA's Goldfields

Kambalda Truck Parking and Hardstand

A new heavy vehicle parking bay and rest stop outside Kambalda for Main Roads WA, with Aboriginal engagement targets exceeded four and five times over.

Location
Kambalda, WA
Client
Main Roads WA
Duration
December 2021 to May 2022
Aboriginal employment
40.9% (target 10%)
Aboriginal business
50.1% (target 10%)

In December 2021 CareyMC was awarded the work order to construct a heavy vehicle parking bay just outside Kambalda. Small in scale, it still involved most aspects of road construction: embankment foundation earthworks, drainage, pavement construction, sealing, and signs and lines.

Because of the site’s geometry and drainage requirements, the embankment for the bay was built up by 1.3 m, which meant importing 22,000 tonnes of gravel from the Spargoville pit.

An excavator loads red earth on the parking bay site

40.9%

Aboriginal employment

Against a target of 10%

50.1%

Aboriginal business engagement

Against a target of 10%

22,000 t

Gravel imported

From the Spargoville pit

1.3 m

Embankment raise

For site geometry and drainage

The challenges

The project was delivered while COVID-19 was prevalent in the community, and the team took the precautions that required. The Kambalda to Esperance gas pipeline also ran through the middle of the work area: inspectors had to be present whenever work came within 10 m of the line, and compaction was restricted.

Aboriginal engagement

The work order set targets for Aboriginal engagement, and both were significantly exceeded. Aboriginal employment reached 40.9% against a target of 10%, and engagement of Aboriginal businesses reached 50.1% against a target of 10%.

All critical safety and quality requirements were met.

The finished sealed surface of the parking bay An excavator and road train on the embankment works An excavator trims the red earth embankment The project crew in high-visibility clothing lined up on site A road train on site beside the crew The crew gathers at the site office for a briefing The highway beside the site, with fresh line marking

More projects

All civil projects
  • A freshly sprayed seal runs straight through red country and bush, with a bitumen sprayer working in the distance

    Main Roads WA (Wongutha Way Alliance) · Laverton WA · Dec 2019 - Sept 2021

    Outback Highway, Great Central Road

    An alliance with Main Roads WA and Central Earthmoving to seal the first 40 km of the Great Central Road east of Laverton, part of the 2,700 km Outback Way.

  • A freshly sealed highway with new line marking curves past road signs for Great Ocean Drive and Esperance

    Main Roads WA · Esperance WA

    South Coast Highway Upgrade

    Road widening and safety improvements at two Black Spot intersections on the main road into Esperance, for Main Roads WA.

  • Mobile cranes lift a conveyor gallery section at Esperance Port, with the ship loader and stacked containers behind

    Southern Ports Authority · Esperance WA · Jul - Oct 2021

    Esperance Port Shiploader and Conveyor Demolition

    More than 520 tonnes of redundant steel structure removed at Berth 2, clearing a safe and accessible wharf for Southern Ports.

Ground to move? Let's talk.

Talk with our Civil Team