Hunt Point Revetment Remediation

Replaced the gangway, relocated essential services and reinstated security fencing, working within tidal constraints while nearby tug berths and port operations kept running.

Location
Hunt Point, Port Hedland WA
Year
2024
Scope
Port and coastal remediation

Carey's remediation of the Hunt Point revetment eliminated work health and safety risks, enabling the facility to return to full operational service.

The works were completed within tidal constraints while preserving the functionality of the nearby tug berths, and the upgrades were integrated without disrupting adjacent port operations.

The rebuilt rock revetment behind a new steel guard rail, with port buildings beyond

Scope of work

  • Revetment remediation
  • Gangway replacement
  • Relocation of essential services
  • Reinstatement of security boundary fencing

The result

Work health and safety risks eliminated and the facility back in full operational service, with the nearby tug berths kept working.

A fenced walkway with yellow handrails runs along the revetment towards the harbour The access road at the edge of the site, with Road Ends signs and the port beyond Geotextile fabric laid over rock on the shore of the tug harbour, with a moored tug and the gangway behind

More projects

All civil projects
  • The bow of a large car carrier berthed at Fremantle Port, with utility vehicles and a site container on the wharf beside it

    Fremantle Port Authority · Fremantle Port WA · Jul - Oct 2023

    Fremantle Port Fender Replacement

    Removed the end-of-life steel pylon fender system at H Berth and tied a new fender system into the existing concrete deck, working around ships at a live port.

  • A crane lowers a load beside a scaffold platform at the wharf edge, with container cranes and berthed ships across the harbour

    Fremantle Ports · Fremantle WA · 2026

    Fremantle Inner Harbour Bollard Replacement & Refurbishment

    Replacement and refurbishment of mooring bollards across the Fremantle Inner Harbour, at North Quay and Victoria Quay.

  • Steel truss gangway reaching out over the water to a ferry pontoon on the Tiwi Islands

    Tiwi Enterprise Pty Ltd · Tiwi Islands NT · Sept 2018 - Nov 2019

    Tiwi Islands Ferry Terminals and Visitor Centre

    Built a visitor centre and two ferry landings, one on each side of the Apsley Strait, with 75% of the contract value delivered by Northern Territory businesses.