Tiwi Islands Ferry Terminals and Visitor Centre

A visitor centre and two ferry landings, one on each side of the Apsley Strait, delivered by two Indigenous-owned businesses.

Client
Tiwi Enterprise Pty Ltd
Location
Tiwi Islands NT
Duration
September 2018 to November 2019
Contract
Early contractor involvement, then lump sum

Carey’s involvement dates back to 2016, when it gave Tiwi Enterprise budgeting and constructability advice to help secure funding for a safe way to board and leave the Darwin ferry service, and for a passenger terminal building.

In mid-2018, with funding secured, Tiwi Enterprise and Carey entered an early contractor involvement contract to oversee the design and development of the project. Once the proposal was developed, the relationship moved to a lump sum contract to deliver a visitor centre and two ferry landings, one on each side of the Apsley Strait.

A ferry pontoon and gangway on green water, with mangroves behind

75%

Of contract value

Delivered locally by Northern Territory businesses

30%

Of work hours

By Tiwi Islanders and Tiwi Island businesses, with over $1 million of services

Ten

Tiwi Islanders upskilled

Including Working at Heights and Confined Spaces

Scope of works

  • Construction of the new visitor centre building, steel framed and clad
  • Water, sewer and power upgrades and connection to the new building
  • Fabrication of steel berthing pontoons and aluminium access platforms
  • Installation of steel piles and prefabricated structures to form the two new berths on Bathurst and Melville Islands

Key outcomes

  • A key piece of community infrastructure developed and delivered by two Indigenous-owned businesses, Tiwi Enterprise and Carey
  • 75% of the contract value delivered locally by Northern Territory businesses
  • 30% of work hours and over $1 million of services provided by Tiwi Islanders and Tiwi Island businesses
  • Ten local Tiwi Islanders completed upskilling courses, including Working at Heights and Working in Confined Spaces

The facility was officially opened on 30 January 2020, at a ceremony attended by Senator Sam McMahon.

The new visitor centre building The truss gangway and pontoon seen from the water A barge and crane working on the berth Aerial view of the landing on the Apsley Strait A ferry alongside the new pontoon and gangway The visitor centre behind its new fence Steel piles and scaffolding during pontoon installation

More projects

All civil projects
  • Aerial view of the renewed container hardstand at Esperance port, beside the ship loader

    Southern Ports Authority · Esperance WA · 2023 · $9.25M

    Berth 2 Hardstand Renewal

    A renewed container hardstand and a 220 kL stormwater holding tank at Esperance Port, delivered while the berth stayed open.

  • The bow of a large car carrier berthed at Fremantle Port, with utility vehicles and a site container on the wharf beside it

    Fremantle Port Authority · Fremantle Port WA · Jul - Oct 2023

    Fremantle Port Fender Replacement

    Demolition and replacement of the ship fender system at H Berth, carried out at a working port.

  • Mobile cranes lift a conveyor gallery section at Esperance Port, with the ship loader and stacked containers behind

    Southern Ports Authority · Esperance WA · Jul - Oct 2021

    Esperance Port Shiploader and Conveyor Demolition

    More than 520 tonnes of redundant steel structure removed at Berth 2, clearing a safe and accessible wharf for Southern Ports.

Ground to move? Let's talk.

Talk with our Civil Team