Bis Industries Kwinana Terminal Drainage and Lined Pond
An evaporation basin converted into a lined water treatment pond, with new site drainage, while the bulk cargo terminal kept operating around the works.
- Client
- Bis Industries
- Location
- Kwinana WA
- Duration
- September to November 2017
- Contract
- Lump sum
Bis Industries manages an industrial terminal in Kwinana that transfers and handles bulk products between sea, road and rail. As part of an upgrade to the facility, an existing evaporation basin needed to be converted into a lined water treatment pond. Carey was awarded the contract to carry out the works.
Scope of works
- Clearing vegetation from the site
- Draining the existing basin, with approved disposal of waste liquids
- Supplying, placing and compacting backfill to 50% of the existing basin
- Excavating, shaping and compacting the new lined pond
- Managing the supply and installation of the new pond liner
- Installing site drainage
Working around a live terminal
The team worked in and around the terminal’s day-to-day operations, with frequent consultation between the works supervisor and the terminal manager so both could proceed. Neither the construction project nor the terminal’s operations were delayed in any way.
Gallery
More projects
-

Karratha TAFE Secure Vehicle Compound
A secure compound for 20 fleet vehicles and a bus, designed and built with concrete pavement, security fencing, automatic gates, lighting and swipe card access.
-

OB35 Creek Diversion, TSF1 & TSF3
A large, multi-discipline civil earthworks and drainage package for essential mine infrastructure upgrades at Newman.
-

Sami Bitumen Terminal
A complete civil and building package for a new bitumen import and processing terminal in the Fremantle Ports area, won in an open competitive tender.