Sami Bitumen Terminal

A complete civil and building package for a new bitumen import and processing terminal in the Fremantle Ports area, won in an open competitive tender.

Client
Colas Australia
Location
Kwinana WA
Duration
July 2017 to March 2018
Contract
Lump sum

To better service the Western Australian market, Sami Bitumen Technologies, a member of the French Colas Group, needed a second import and processing terminal in the Fremantle Ports area to support its existing operations in North Fremantle. Following an open competitive tender, Carey was awarded the contract to manage the construction of civil infrastructure and buildings at the new Kwinana site.

More than 1,000 m³ of concrete was poured. Carey staff helped the design consultants and the owner resolve and rationalise constructability details, which reduced the overall concrete needed.

Reinforcing steel laid out for a large concrete slab

1,000+ m³

Of concrete

Poured across the site

Six

Disciplines in one package

Earthmoving, concrete, steel, HVAC, electrical and plumbing

Lump sum

Contract

July 2017 to March 2018

Scope of works

  • Management of asbestos-contaminated materials on the site
  • Underground service culverts, conduits and draw pits
  • A site drainage system, including infiltration ponds, flush pits, manholes and pipework
  • Concrete foundations, slabs and bund walls
  • Fabrication and installation of loading gantry steelwork
  • Construction and fit-out of the mechanical control centre building

Why it mattered

The project let Carey show its capability in managing complex, multi-discipline work, with trades ranging from earthmoving, concrete and steel construction to heating, ventilation and air conditioning, electrical and plumbing.

It also advanced Indigenous participation: one of Carey’s Indigenous trainee labourers furthered his career with funding for a non-slewing crane operator licence.

A finished concrete bund wall A gravel-filled excavation for the site drainage An excavator digs a trench across the site A mini excavator works beside a new concrete pit A concrete pump truck with its boom raised at dawn A drainage pipe laid in a deep trench Formwork and reinforcing for a concrete footing

More projects

All civil projects
  • Aerial view of the Two Rocks foreshore: new paths along the rock wall, the rainbow-roofed Birdman shelter, two jetties and the boat ramp car park

    Department of Transport · Two Rocks Marina WA · Feb - Oct 2022

    Two Rocks Southern Foreshore Redevelopment

    Architectural shelters, landscaping and public amenities along more than 800 m of foreshore beside Two Rocks Marina.

  • Open trench with a new pipeline beside conveyors and stacked containers at Esperance Port

    Southern Ports Authority · Esperance WA · Aug - Oct 2020

    Esperance Port Diesel Pipeline

    A new DN350 diesel pipeline and connection pit at Esperance Port, replacing buried and under-wharf pipework with no interruption to through traffic.

  • Road bridge over a rock-armoured channel of clear green water at Bandy Creek

    Italia Stone Group / Department of Transport · Esperance WA · Aug 2019 - Apr 2020

    Bandy Creek Weir Reinstatement

    Bridge construction and the structural and services works for the new Bandy Creek weir at Esperance, delivered under subcontract.

Ground to move? Let's talk.

Talk with our Civil Team