Road bridge over a rock-armoured channel of clear green water at Bandy Creek

Bandy Creek Weir Reinstatement

Bridge construction and the structural and services works for the new Bandy Creek weir at Esperance, delivered under subcontract.

Client
Italia Stone Group / Department of Transport
Location
Esperance WA
Duration
August 2019 to April 2020
Contract
Lump sum

Since the Bandy Creek Boat Harbour was built in the mid-1980s, a weir at the rear of the dredged river mouth has protected the upstream Lake Warden System Ramsar site from drying out, kept sediment out of the boat harbour and provided a crossing over the creek.

The original structure, and a second built on the same spot in 2010, were both damaged beyond repair by major weather events and flooding. The third is a rock weir with a 10 m deep vinyl sheet pile cut-off wall and a separate bridge, 50 m upstream of the first site. Carey was awarded the bridge construction, structural and services works under subcontract.

85 m

Sheet pile cut-off wall

Vinyl, along the weir alignment

20 m

Driven tubular piles

For the bridge foundations

28%

Of project labour

By Aboriginal employees

8%

Of contract value

Delivered by Aboriginal businesses

Scope of works

  • An 85 m vinyl sheet pile cut-off wall along the weir alignment
  • 20 m driven tubular piles for the bridge foundations
  • Precast headstocks and road planks
  • Critical services (sewer, water and telecommunications) across the new bridge
  • Management of the demolition of the existing weir

Aboriginal participation

As an Aboriginal business, Carey set out to provide opportunities for local Aboriginal people and businesses wherever possible. Aboriginal employees made up 28% of project labour, and 8% of the contract value was delivered by Aboriginal businesses.

Training and upskilling were provided in boat operation (coxswain), crane dogging and mobile plant operation. Carey also helped the local Native Title Aboriginal Corporation establish its business arm, with support and advice.

Aerial view of the new bridge and rock weir across Bandy Creek, with the boat harbour beyond A mobile crane working beside the new bridge during construction

More projects

All civil projects
  • Steel truss gangway reaching out over the water to a ferry pontoon on the Tiwi Islands

    Tiwi Enterprise Pty Ltd · Tiwi Islands NT · Sept 2018 - Nov 2019

    Tiwi Islands Ferry Terminals and Visitor Centre

    A visitor centre and two ferry landings, one on each side of the Apsley Strait, delivered by two Indigenous-owned businesses.

  • Aerial view of the renewed container hardstand at Esperance port, beside the ship loader

    Southern Ports Authority · Esperance WA · 2023 · $9.25M

    Berth 2 Hardstand Renewal

    A renewed container hardstand and a 220 kL stormwater holding tank at Esperance Port, delivered while the berth stayed open.

  • The bow of a large car carrier berthed at Fremantle Port, with utility vehicles and a site container on the wharf beside it

    Fremantle Port Authority · Fremantle Port WA · Jul - Oct 2023

    Fremantle Port Fender Replacement

    Demolition and replacement of the ship fender system at H Berth, carried out at a working port.

Ground to move? Let's talk.

Talk with our Civil Team