Newman Housing Uplift

Renovation of residential homes for Newman-based mining staff and their families, with a 40% Indigenous workforce.

Location
Newman, WA
Client
On request
Duration
July 2023 to March 2024
Contract type
Lump sum
Indigenous workforce
40%

The client provides accommodation to its Newman-based staff and has undertaken a major upgrade program to improve the quality of the housing. Some of the properties are more than 50 years old, and many contain asbestos and other hazardous materials. This project was the second stage of a multi-stage initiative.

A renovated bathroom with a new vanity, mirror and glass shower screen

40%

Indigenous workforce

Five

Indigenous people directly employed

Most with little or no previous construction experience

50+ years

Age of some of the homes

Many containing asbestos and other hazardous materials

Scope of works

  • Surveys of the as-built condition and a dilapidation report for each property
  • Design and documentation for each property by Carey’s Indigenous architects
  • Demolition of existing fitouts and removal of hazardous materials
  • New kitchens, bathrooms, flooring, sheds and carports
  • Upgraded lighting, electrical fixtures and air conditioning
  • Painting and miscellaneous repairs

The challenges

  • Relocating tenants into temporary accommodation
  • Coordinating trades across multiple worksites to the client’s health and safety standards
  • Delivering amid fluctuating flight and accommodation availability caused by other projects
  • Procuring and delivering long-lead items on tight schedules, with quality control
  • Value engineering to make the most of the investment and the life of the new fitouts

Indigenous workforce

The project had a 40% Indigenous workforce, directly employing five Indigenous people, most with little or no previous construction experience. One went on to start a plumbing apprenticeship, and others pursued careers as operators and mechanics.

The project was completed to a high standard and within budget.

Floor plan drawing of a renovated home, showing the kitchen, bathrooms and bedrooms A concrete truck delivers to one of the homes Workers finish a new concrete slab under a carport Two workers in high-visibility shirts at a concrete pour A worker fits skirting along a new timber-look floor The crew wheel concrete from the truck to the pour

More projects

All civil projects
  • Inside a refurbished steel-framed shed with new cladding and a mobile scaffold standing on the concrete floor

    Cocos (Keeling) Islands

    Cocos Islands Vehicle Shelter

    Repair and refurbishment of a corroded equipment shed on the Cocos (Keeling) Islands, before the asset was too far gone to salvage.

  • Refitted dental surgery with a blue chair, new cabinetry and vinyl flooring

    Department of Infrastructure · Cocos (Keeling) Islands · Sept - Oct 2020

    Cocos Islands Dental Clinic

    A turn-key refit of the dental clinic at the Home Island Medical Centre, with specialist cabinetry, upgraded services and recommissioned dental equipment.

  • Refurbished room with fresh white walls and an open blue door

    Jones Lang LaSalle (WA) · West Island and Home Island, Cocos (Keeling) Islands · Jan - Feb 2020

    Cocos Islands High School Asbestos Removal and Refurbishment

    Asbestos-contaminated former toilets at both school campuses turned into storerooms, on a fast turnaround.

Ground to move? Let's talk.

Talk with our Civil Team