A large, multi-discipline civil earthworks and drainage package for essential mine infrastructure upgrades at Newman.

Broad bulk earthworks landform stretching across red Pilbara ground

The OB35, TSF1 wall lift and TSF3 buttress works brought together a tailings dam lift, pipeworks, electrical and instrumentation works, culvert supply and installation, concrete works, steel fabrication and bulk earthworks.

OB35 Creek Diversion

  • A flood protection bund, including installation and trimming of safety berms
  • Six-barrel, 1.2 m diameter corrugated steel pipe culverts, with a section of haul road over them
  • Bulk excavation and construction of a 235 m land bridge in the diversion channel at the Overburden Storage Area
  • The downstream and upstream ends of the creek diversion, including riprap sorting and placement

TSF1 wall raise

  • A 3 m raise of the existing TSF1 wall, with access ramps, a new decant access causeway and surface water treatment
  • Decant pontoon design and construction, pumps and equipment
  • Replacement of about 920 m of HDPE tailings delivery pipeline, with works completed during a shutdown
  • Installation of motor, pump and valves
  • Removal and replacement of 1,600 m of Victaulic tailings deposition pipe and 800 m of HDPE decant return pipe
  • Electrical infrastructure: power poles, communications, CCTV, instrumentation and control

TSF3 buttress

Removal of vegetation, then construction of the buttress wall and a saddle dam using 400,000 m³ of approved fill from the Overburden Storage Area.

With limited workfront across the three areas, contractors had to work at the same time on the different packages and complete specific structural, mechanical and piping works during the shutdown period.

The work was awarded to Carey on the strength of similar bulk earthworks packages completed before it, a strong safety record and the capability of the Carey management team.

Back to Carey News
Location
Newman, Pilbara WA
Client
BHP
Period
2023 to 2024
Scope
Multi-discipline
Fill placed
400,000 m³