The client provides accommodation to its Newman-based staff and has undertaken a major upgrade program to improve the quality of the housing. Some of the properties are more than 50 years old, and many contain asbestos and other hazardous materials. This project was the second stage of a multi-stage initiative.
Scope of works
- Surveys of the as-built condition and a dilapidation report for each property
- Design and documentation for each property by Carey’s Indigenous architects
- Demolition of existing fitouts and removal of hazardous materials
- New kitchens, bathrooms, flooring, sheds and carports
- Upgraded lighting, electrical fixtures and air conditioning
- Painting and miscellaneous repairs
The challenges
- Relocating tenants into temporary accommodation
- Coordinating trades across multiple worksites to the client’s health and safety standards
- Delivering amid fluctuating flight and accommodation availability caused by other projects
- Procuring and delivering long-lead items on tight schedules, with quality control
- Value engineering to make the most of the investment and the life of the new fitouts
Indigenous workforce
The project had a 40% Indigenous workforce, directly employing five Indigenous people, most with little or no previous construction experience. One went on to start a plumbing apprenticeship, and others pursued careers as operators and mechanics.
The project was completed to a high standard and within budget.
Back to Carey News- Location
- Newman, WA
- Client
- On request
- Duration
- July 2023 to March 2024
- Contract type
- Lump sum
- Indigenous workforce
- 40%