In December 2021 CareyMC was awarded the work order to construct a heavy vehicle parking bay just outside Kambalda. Small in scale, it still involved most aspects of road construction: embankment foundation earthworks, drainage, pavement construction, sealing, and signs and lines.
Because of the site’s geometry and drainage requirements, the embankment for the bay was built up by 1.3 m, which meant importing 22,000 tonnes of gravel from the Spargoville pit.
The challenges
The project was delivered while COVID-19 was prevalent in the community, and the team took the precautions that required. The Kambalda to Esperance gas pipeline also ran through the middle of the work area: inspectors had to be present whenever work came within 10 m of the line, and compaction was restricted.
Aboriginal engagement
The work order set targets for Aboriginal engagement, and both were significantly exceeded. Aboriginal employment reached 40.9% against a target of 10%, and engagement of Aboriginal businesses reached 50.1% against a target of 10%.
All critical safety and quality requirements were met.
Back to Carey News- Location
- Kambalda, WA
- Client
- Main Roads WA
- Duration
- December 2021 to May 2022
- Aboriginal employment
- 40.9% (target 10%)
- Aboriginal business
- 50.1% (target 10%)