Fremantle Port fender replacement

Demolition and replacement of the ship fender system at H Berth, carried out at a working port.

The bow of a large car carrier berthed at Fremantle Port, with utility vehicles and a site container on the wharf beside it

The fender system at H Berth had reached the end of its life and was outdated and damaged. Carey was awarded the tender to remove the redundant system and replace it with a new, modern fender system.

Scope of work

  • Removal of the existing steel pylon fender system
  • Tie-in of the new fender support to the existing concrete deck
  • Working around a live port, protecting ships and mooring lines during demolition
  • Meeting tight timelines during port shutdowns and between shipping schedules

New techniques

  • A hydro-demolition robot, used to remove selected areas of concrete without damaging the reinforcing
  • A mobile booth to contain demolition activities and protect ships in berth
  • Mobile counterweight scaffolds: temporary supports that can be moved easily when a ship needs to berth

Several of these initiatives have since become standard practice at Fremantle Port.

The project is a strong example of Carey’s ability to deliver technically complex work in challenging environments, to demanding schedules and site constraints.

Back to Carey News
Location
H Berth, Fremantle Port
Client
Fremantle Port Authority
Duration
July to October 2023
Contract type
Lump sum